SAR on PREE Framework 2024-2025
| Activity Planner for SAR as per PREE | ||
|---|---|---|
| # | Activities | Status |
| 1.. | Program Teams Nomination from concerned Deans | Completed |
| 2. | Issuance of PT Notification Letter from Registrar Office | Completed |
| 3 | Training on Development of SAR as per PREE for PT members | Completed |
| 4. | Development of SAR as per PREE by PT members | Completed |
| 5. | Assessment Teams (ATs) Nomination from concerned Deans | Completed |
| 6 | Issuance of AT Notification Letter from Registrar | Completed |
| 7. | Training on Assessment of SAR as per PREE for Assessment Teams | Completed |
| 8. | Arrangement of AT Visit to Departments | Completed |
| 9. | Issuance of AT Findings’ letters to concerned Chairpersons | Completed |
| 10. | Corrective Actions received from concerned Chairpersons | Completed |
| 11. | Executive Summary Preparation and Approval | Completed |
| 12. | Follow up for implementation plan | Completed |
| 13. | Report on Follow Up | In Progress |
Note: Relevant documents are kept in QEC office, will be furnished upon request